top of page


TSA Recapitalization Optimization Project
Total Amount: $5,339,744.00
Completion Date: March, 2016
​
Scope of Work:
Renovation of the West side of ITF area such as renovation and relocation of existing content in storage area. Construction of North side building above loading dock. Finish such out work such as MEP, sprinkler, lighting, and HVAC system. Build out & finish work for South side building. Construction of oversized canopy. Renovate existing ITF area such as installation of new conveyor equipment. Construction of new interior offices, BHS control room, OSR room, and MUX room. Relocation of FM200 Fire Suppression (demolition & installation of new fire suppression system). Works also included retrofitting of structural